Measuring the Impact of External Risk Factors on Costs for Drainage Construction Projects in Aceh-Indonesia

Authors

  • Mahmuddin Mahmuddin Department of Civil Engineering, Universitas Syiah Kuala, Banda Aceh, Indonesia
  • Mubarak Mubarak Department of Civil Engineering, Universitas Syiah Kuala, Banda Aceh, Indonesia
  • Fachrurrazi Fachrurrazi Department of Civil Engineering, Universitas Syiah Kuala, Banda Aceh, Indonesia
  • Ziana Ziana Department of Civil Engineering, Universitas Syiah Kuala, Banda Aceh, Indonesia
  • Suci Tiara Agus Master of Civil Engineering Study Program, Universitas Syiah Kuala, Banda Aceh, Indonesia

DOI:

https://doi.org/10.22373/ekw.v12i1.21011

Keywords:

risk impact, external factors, drainage project, cost, Aceh

Abstract

Abstract: Infrastructure projects are always faced with uncertainty and risks, both from within and outside the project, including drainage projects. An understanding of the sources and impacts of risks is required for construction implementers to minimize the negative effects of these risks. One of the impacts commonly experienced by construction companies is the emergence of cost overruns, which can potentially lead to project failure. This study aimed to analyze the impact of risk on cost for external factors in the implementation of drainage projects in Aceh Province in 2021. Employing a mixed-method approach, primary data were gathered through the distribution of questionnaires to 52 respondents actively engaged in project implementation. The questionnaire was designed to collect information on the impact of risk on costs for 3 external factors, namely social (2 variables), government policy (2 variables), and disaster (4 variables). The impact of risks was assessed using the severity index (SI) analysis. The findings revealed eight external risk variables exerting an influence on the cost of implementing drainage projects in Aceh Province in 2021. The most substantial impact on cost was categorized as "moderate" and manifested in two variables: uncertain weather conditions (SI = 0.400) and flooding (SI = 0.388). Understanding the potential impact of risks on project costs, especially those originating from external factors, will make it easier for contractors to plan risk mitigation and ensure the project is completed on target.

Abstrak: Drainase merupakan salah satu proyek infrastruktur yang tidak lepas dari risiko-risiko yang dapat memengaruhi tujuan proyek. Risiko pada proyek dapat berasal dari faktor eksternal yang berasal dari luar dan tidak berhubungan dengan kegiatan proyek, namun dapat berdampak pada pencapaian tujuan proyek. Penerapan manajemen risiko perlu diaplikasikan, utamanya berkenaan dengan pemahaman terhadap potensi risiko yang dihadapi dan dampak yang ditimbulkan. Pembengkakan biaya merupakan bentuk risiko yang sering terjadi dan dapat berakhir pada kondisi terburuk berupa kegagalan proyek. Tujuan penelitian ini adalah menganalisis dampak risiko terhadap biaya pelaksanaan proyek dari faktor-faktor risiko eksternal. Objek penelitian ini difokuskan pada proyek drainase di Provinsi Aceh yang dilaksanakan pada tahun 2021. Data penelitian ini diperoleh melalui penyebaran kuesioner kepada 52 responden yang terlibat dan berperan langsung dalam pelaksanaan proyek. Kuesioner disusun untuk mengumpulkan informasi dampak dari 3 faktor eksternal, yaitu faktor sosial (2 variabel), faktor kebijakan pemerintah (2 variabel) dan faktor bencana (4 variabel). Dampak risiko terhadap biaya diukur dengan analisis severity index (SI). Dari 8 variabel yang dianalisis, dampak risiko tertinggi yang ditemukan muncul pada 2 variabel dengan level dampak "sedang." Variabel-variabel tersebut adalah kondisi cuaca yang tidak menentu (SI = 0,400) dan banjir (SI = 0,388). Dengan mengenali potensi dampak risiko terhadap biaya, khususnya pada faktor-faktor eksternal, kontraktor dapat lebih awal bersiap dan merencanakan mitigasi risiko untuk memastikan proyek dapat diselesaikan sesuai dengan sasaran.

References

Agus, S. T., Mubarak, M., Fachrurrazi, F., Rizalihadi, M., & Ziana, Z. (2024). The impact of internal risk factors on cost of drainage projects in Aceh Province. AIP Conf. Proc., 3082, 030016. https://doi.org/10.1063/5.0201132

Afana, O., Al Zubaidi, R., Abu Dabous, S., & Ibrahim, F. (2024). Categories and Factors of Cost Overrun in Construction Projects: A Systematic Review. Eng. Technol. Appl. Sci. Res., 14(6), 18330–18347. https://doi.org/10.48084/etasr.9006

Ali, A. (2018). Analisa Risiko Pekerjaan Jaringan Irigasi DI Waru Kabupaten Penajam Paser Utara Provinsi Kalimantan Timur. Jurnal Keilmuan dan Aplikasi Teknik Sipil, 1(1), 1–16.

Amani, N., & Safarzadeh, K. (2022). Project Risk Management in Iranian Small Construction Firms. Journal of Engineering and Applied Science, 69(7), 1–14. https://doi.org/10.1186/s44147-021-00050-8

Anshuka, A., Fu, X., & White, I. (2025). High water, high stakes: A global review of flood risk and housing price effects. International Journal of Disaster Risk Reduction, 122, 105452. https://doi.org/10.1016/j.ijdrr.2025.105452

Ariska, T. Y., Mubarak, M., Husin, S., Maulina, F., & Mahmuddin, M. (2024). Analysis of the risk impact of internal factors on time in building construction projects in Aceh Province. AIP Conf. Proc., 3082, 030017. https://doi.org/10.1063/5.0201129

Azhari, T. M. F., Oktaviani, C. Z., & Mubarak. (2021). Profil Kinerja Konsultan Konstruksi Selama Pandemi Covid-19 Di Kota Banda Aceh. Prosiding Konferensi Nasional Teknik Sipil 15, 627–634.

Babaei, M., Rashidi-baqhi, A., & Rashidi, M. (2022). Estimating Project Cost under Uncertainty Using Universal Generating Function Method. Journal of Construction Engineering and Management, 148(2), 04021194. https://doi.org/10.1061/(ASCE)CO.1943-7862.0002233

Banihashemi, S. A., & Khalilzadeh, M. (2022). A Novel Fuzzy Expert System for Project Portfolio Risk Management: Case Study of a Construction Company. Jordan Journal of Civil Engineering, 16(3), 436–456.

Buba, G. S., Jatau, J., & Jatau-Yeshua, T. S. (2020). Effects of Construction Risk Management on Time, Cost, and Quality of Construction Projects. Proc. Conference: NIQS RESCON, Nigeria.

Chapman, C., & Hall, J. W. (2022). Designing green infrastructure and sustainable drainage systems in urban development to achieve multiple ecosystem benefits. Sustainable Cities and Society, 85, 104078. https://doi.org/10.1016/j.scs.2022.104078

Fathoni, M. Z. (2020). Analisis Risiko pada Proyek Pembuatan Lintel Set Point Dengan Metode Kualitatif (Studi Kasus : PT. XYZ). Jurnal PASTI, 14(2), 113–126. https://doi.org/10.22441/pasti.2020.v14i2.002

Fu, X., Bell, R., Reu Junqueira, J., White, I., & Serrao‐Neumann, S. (2023). Managing rising residual flood risk: A national survey of Aotearoa‐New Zealand. Journal of Flood Risk Management, 16(4), e12944. https://doi.org/10.1111/jfr3.12944

Hollmann, J. K. (2017). Complexity risk and modeling disorder. In Handbook of research on leveraging risk and uncertainties for effective project management (pp. 139-151). IGI Global Scientific Publishing.

Husin, S., Fachrurrazi, F., Rizalihadi, M., & Mubarak, M. (2019a). Implementing Fuzzy TOPSIS on Project Risk Variable Ranking. Advances in Civil Engineering, 2019, 9283409. https://doi.org/10.1155/2019/9283409

Husin, S., Mubarak, M., & Fachrurrazi, F. (2019b). The Significance Risk for Factors of Labour, Material, and Equipment on Construction Project Quality. Aceh International Journal of Science and Technology, 8(2), 106–113. https://doi.org/10.13170/aijst.8.2.13281

Jahan, S., Khan, K. I. A., Thaheem, M. J., Ullah, F., Alqurashi, M., & Alsulami, B. T. (2022). Modeling Profitability-Influencing Risk Factors for Construction Projects: A System Dynamics Approach. Buildings, 12(6), 701. https://doi.org/10.3390/buildings12060701

Karamoozian, A., Wu, D., Chen, C. L. P., & Luo. C. (2019). An Approach for Risk Prioritization in Construction Projects Using Analytic Network Process and Decision-Making Trial and Evaluation Laboratory. IEEE Access, 7, 159842–159854. https://doi.org/10.1109/ACCESS.2019.2939067

Kaufmann, C., & Kock, A. (2022). Does project management matter? The relationship between project management effort, complexity, and profitability. International Journal of Project Management, 40(6), 624-633. https://doi.org/10.1016/j.ijproman.2022.05.007

Khodeir, L. M., & El Ghandour, A. (2019). Examining the role of value management in controlling cost overrun [application on residential construction projects in Egypt]. Ain Shams Engineering Journal, 10(3), 471–479. https://doi.org/10.1016/j.asej.2018.11.008

Majid. A.M.Z., & McCaffer, R. (1997). Assessment of Work Performance of Maintenance Contractors in Saudi Arabia. Journal of Management in Engineering, 13(5), 91. https://doi.org/10.1061/(ASCE)0742-597X(1997)13:5(91)

Marasabessy, R. S., Henaulu, A. K., & Latuconsina, M. (2020). Analisis Risiko Kecelakaan Kerja Menggunakan Metode Hazard dan Operability Study (HAZOP) pada Proyek Konstruksi Drainase. Profisiensi, 8(2), 134–142.

Mubarak, Husin, S., & Oktaviati, M. (2017). External Risk Factors Affecting Construction Costs. AIP Conf. Proc., 1903(1), 110005. https://doi.org/10.1063/1.5011631

Mubarak, Husin, S., & Syarafina. (2016). Risiko Eksternal Pada Pelaksana Proyek Konstruksi Di Provinsi Aceh. Konferensi Nasional Teknik Sipil 10, 131–138.

Olanrewaju, A. L., AbdulAziz, A., Preece, C. N., & Shobowale, K. (2021). Evaluation of measures to prevent the spread of COVID-19 on the construction sites. Cleaner Engineering and Technology, 5, 100277. https://doi.org/10.1016/j.clet.2021.100277

Plebankiewicz, E., & Wieczorek, D. (2020). Adaptation of a cost overrun risk prediction model to the type of construction facility. Symmetry, 12(10), 1739. https://doi.org/10.3390/sym12101739

PMI. (2017). Guide to the Project Management Body of Knowledge (PMBOK® Guide). 6th Edition.

Risandi, B., Masimin, & Rauzana, A. (2017). Analisis Faktor-Faktor Pembengkakan Biaya (Cost Overrun) yang Berpengaruh Terhadap Ketidakpastian Biaya (Contingency Cost) Pada Proyek Irigasi di Kabupaten Aceh Besar. Jurnal Teknik Sipil, 1(2), 317–328.

Rustandi, T. (2017). Kajian Risiko Tahap Pelaksanaan Konstruksi Proyek Peningkatan Jaringan Irigasi Bendung Leuwigoong. Jurnal Infrastruktur, 3(1), 19–30.

Sharma, S., & Kumar Gupta, A. (2020). Identification and Management of Risk in Building and Infrastructure Projects. Journal of Construction Engineering, Technology & Management, 10(2), 1-9. https://doi.org/10.37591/jocetm.v10i2.3951

Singh, Y. K. (2006). Fundamental Research Methodology and Statistics. New Age International Publishers.

Siraj, N. B., & Fayek, A. R. (2019). Risk Identification and Common Risks in Construction: Literature Review and Content Analysis. Journal of Construction Engineering and Management, 145(9). https://doi.org/10.1061/(ASCE)CO.1943-7862.0001685

Sovacool, B. K., & Ryu, H. (2025). Beyond economies of scale: Learning from construction cost overrun risks and time delays in global energy infrastructure projects. Energy Research & Social Science, 123, 104057. https://doi.org/10.1016/j.erss.2025.104057

Sugiyanto, S., & Kosbiamtoro, A. (2022). Analisis Kinerja Biaya Pada Proyek Rehabilitasi Drainase Dan Trotoar Jalan Teuku Umar Paket I dengan Metode Earned Value. Jurnal Litbang Sukowati: Media Penelitian dan Pengembangan, 5(2), 126–141. doi: 10.32630/sukowati.v5i2.320.

Tian, K., Zhu, Z., Mbachu, J., Ghanbaripour, A., & Moorhead, M. (2025). Artificial intelligence in risk management within the realm of construction projects: A bibliometric analysis and systematic literature review. Journal of Innovation & Knowledge, 10(3), 100711. https://doi.org/10.1016/j.jik.2025.100711

Weinbren, M., Inkster, T., & Lafferty, F. (2021). Drains and the Periphery of the Water System – What do You do When the Guidance is Outdated. Infection Prevention in Practice, 3(4), 100179. https://doi.org/10.1016/j.infpip.2021.100179